Power Supply
Task / Description Slow   Ave   Fast    Units
 AC Install 2 no Service transformers, 6 men -   12.0  -    days
 AC Install 2 no Switchgear, 7 men -   12.0  -    days
 AC Install Associated Trays and ladders, 3 men 11.0  5.0  -    days
 AC Cable Terminations in Tx and SWG Rooms, 3 men 12.0  6.0  -    days
 DC Install Insulated Flooring in DC Room, 1 men -   5.0  -    days
 DC Install 1 set Rectifier Transformer and Rectifier, 7 men -   1.0  -    days
 DC Install Switchgear, 7 men -   10.0  -    days
 DC Primary Cable Terminations and Busduct, 18 men 12.0  9.0  -    days
 DC Secondary Cable Terminations and Connections, 9 men 12.0  6.0  -    days
 Trackside Cabling 33kV/Pilot Cables, 10 men 2,100.0  -   -    m run/day
 Trackside Cabling Terminations, 6 men -   1.0  -    days