Framing and Bracing

Construction Man-hour Norms

Description These labour constants refer to un-automated methads of construction Unit    Tradesman Hours Labourer Hours
Heavy sections, including connections—UB, UC, RSJ and RSC        
  Fabrication tonne 23.00  
  Erection tonne 7.00  
Light sections—angles etc.        
  Fabrication tonne 40.00  
  Erection tonne 20.00  
Hollow sections, including connections        
  Large sections, fabrication tonne 30.00  
  Large sections, erection tonne 10.00  
  Small sections, fabrication tonne 35.00  
  Small sections, erection tonne 15.00  
Trusses, including connections        
  Up to 10m span, fabrication tonne 50.00  
  Up to 10m span, erection tonne 10.00  
  Over 10m span, fabrication tonne 35.00  
  Over 10m span, erection tonne 6.00  
Proprietary purlins and girts        
  Up to 150mm high m 0.09  
  Over 150mm high m 0.12  
Surface Treatment        
Sand blast and paint        
  Light sections tonne 8.00  
  Heavy sections tonne 5.00  

Customer feedback counts

The Experts

Client Reviews

  GoodFirms Badge   Crozdesk   Methvin is a leader in Construction Estimating on G2  Login   Vinci   Holder   Hoar