Reinforcement

 Reinforcement, Placing and Fixing Construction Man-hour Norms

Description Mesh Reinforcement, placing and fixing in Unit    Tradesman Hours Labourer Hours
Mesh        
  Slabs, small areas m2 0.12  
  Slabs, large areas m2 0.08  
Walls   m2 0.12  
  Bar Reinforcement, placing and fixing      
  6mm-12mm stirrups tonne 30.00  
  16mm-32mm bars in slabs tonne 18.00  
  16mm-32mm bars in walls tonne 20.00  
  16mm-32mm bars in columns and beams tonne 20.00  

 

Reinforcement Fixing - Planning Production Rates

Task / Description

Slow Ave Fast Units
Slabs/Foundations, steelfixing, 6mm 40.3 38.4 36.5 hrs/tonne
Slabs/Foundations, steelfixing, 8mm 28.2 26.9 25.8 hrs/tonne
Slabs/Foundations, steelfixing, 10mm 22.5 20.6 20.1 hrs/tonne
Slabs/Foundations, steelfixing, 12mm 16.9 16.3 15.4 hrs/tonne
Slabs/Foundations, steelfixing, 16mm 12.0 11.5 10.9 hrs/tonne
Slabs/Foundations, steelfixing, 20mm 9.2 8.6 8.2 hrs/tonne
Slabs/Foundations, steelfixing, 25mm 6.9 6.7 6.5 hrs/tonne
Slabs/Foundations, steelfixing, 32mm 5.7 5.5 5.2 hrs/tonne
Slabs/Foundations, steelfixing, 40mm 5.3 5.1 4.9 hrs/tonne
Slabs/Foundations, steelfixing, 50mm 5.2 4.9 4.6 hrs/tonne
Beams/Columns, steelfixing, 6mm 55.4 52.8 50.6 hrs/tonne
Beams/Columns, steelfixing, 8mm 38.8 37.0 35.1 hrs/tonne
Beams/Columns, steelfixing, 10mm 29.5 28.4 26.9 hrs/tonne
Beams/Columns, steelfixing, 12mm 23.4 22.4 21.9 hrs/tonne
Beams/Columns, steelfixing, 16mm 16.6 15.8 15.1 hrs/tonne
Beams/Columns, steelfixing, 20mm 12.4 11.9 11.3 hrs/tonne
Beams/Columns, steelfixing, 25mm 9.9 9.2 8.7 hrs/tonne
Beams/Columns, steelfixing, 32mm 6.8 6.6 6.2 hrs/tonne
Beams/Columns, steelfixing, 40mm 6.1 5.9 5.6 hrs/tonne
Beams/Columns, steelfixing, 50mm 6.1 5.9 5.6 hrs/tonne
Walls, steelfixing, 6mm 41.2 40.8 39.1 hrs/tonne
Walls, steelfixing, 8mm 29.2 28.6 27.4 hrs/tonne
Walls, steelfixing, 10mm 22.7 22.0 21.2 hrs/tonne
Walls, steelfixing, 12mm 17.6 17.3 16.9 hrs/tonne
Walls, steelfixing, 16mm 12.4 12.2 11.8 hrs/tonne
Walls, steelfixing, 20mm 9.4 9.2 8.7 hrs/tonne
Walls, steelfixing, 25mm 7.4 7.2 7.0 hrs/tonne
Walls, steelfixing, 32mm 7.0 6.8 6.4 hrs/tonne
Walls, steelfixing, 40mm 6.4 6.1 5.9 hrs/tonne
Walls, steelfixing, 50mm 5.3 5.1 4.8 hrs/tonne
Staircases, steelfixing, 6mm 48.9 48.0 45.5 hrs/tonne
Staircases, steelfixing, 8mm 34.4 33.6 31.9 hrs/tonne
Staircases, steelfixing, 10mm 26.6 25.8 24.3 hrs/tonne
Staircases, steelfixing, 12mm 20.9 20.4 19.5 hrs/tonne
Staircases, steelfixing, 16mm 14.6 14.4 13.8 hrs/tonne
Staircases, steelfixing, 20mm 11.3 10.8 10.5 hrs/tonne
Staircases, steelfixing, 25mm 8.6 8.4 8.2 hrs/tonne

 

Post Tensioning

Task / Description Slow Ave Fast Units
Lag for Initial Stress Tensioning after 1st bay cast - 48.0 - hrs
Lag for Final Stress Tensioning after Initial Stress - 120.0 - hrs