Restoration Works

Planning Production Rates

Task / Description Slow Ave Fast Units
Façade Cleaning, Water Jetting - Water Blasting - 25.0 - m2/day
Façade Cleaning, Acid Etching - 9.0 - m2/day
Façade Cleaning, Grit Blasting - 12.0 - m2/day
Cladding Restoration, Brickwork - 6.5 - m2/day
Cladding Restoration, Stonework courses - 20.0 - m/day