Building Constants

Planning and Estimating Production Rates

Task / Description Slow Ave Fast Units
Granolithic Flooring - 3.1 - m2/hr
Terrazzo Flooring, in-situ - 3.6 - m2/hr
Terrazzo Flooring, pre-cast - 4.6 5.1 m2/hr
Mosaic Tiling, 0.045x0.045m - 1.5 2.2 m2/hr
Clay, quarry Tiles, small areas, much cutting - 0.8 1.1 m2/hr
Clay, quarry Tiles, large areas, little cutting - 2.2 2.8 m2/hr
Raised Floor System - 2.6 - m2/hr
Linolium/Thermo-Plastic Flooring - 3.1 5.0 m2/hr
Thermo-Plastic Floor Tiles - 3.3 5.6 m2/hr
Wood Block Flooring, lay blocks - 1.5 2.1 m2/hr
Wood Block Flooring, sand and polish - 3.1 - m2/hr
Carpeting, Underlay & Gripper - 5.6 6.1 m2/hr
Carpeting, Adhesive Fixing - 3.5 4.2 m2/hr
Carpeting, Fully Fitted - 2.0 2.8 m2/hr
Hardboard Sheeting Coverings, small areas - 3.7 4.1 m2/hr
Hardboard Sheeting Coverings, large areas - 6.6 7.2 m2/hr
Floor Sheeting Coverings, Lay Lino - 9.5 10.5 m2/hr