Friday, July 03, 2009
Register  |  Login
Production Rates
  Recent Articles  

Acceptance Guideline For Longitudinal Cracking In Reinforced Concrete Pipe
Reinforced concrete pipe, when designed in accordance with AS/NZS4058 and AS/NZS3725 can last for over 100 years. However, when the synergy required between manufacturers, designers, installers and asset managers is not met, the integrity of the concrete pipe may be affected.

Database or spreadsheet. What’s the difference, anyway?
To address this question it’s easiest to look at estimating from a historical perspective: Once upon a time, every contractor created estimates by hand. He/she would pull out a pad of paper and pencil, jot down some figures line by line, then sum up each item to achieve the estimate. This was a simple and effective way to create a bid, but human error, inflexibility, and time consumption left plenty of room for improvement.

The Determination of Damage to Reinforced Concrete Beams Designed to 1972 Ministry of Works Design Codes
Currently there is no prescribed method for determining the amount of damage sustained by a reinforced concrete structure designed to pre 1972 New Zealand design standards during an earthquake. One of the key features of these designs is the amount of shear damage that is observed and the lack of knowledge today, in assessing and repairing this form of damage.

Law relating to contracting
The law states that a contract shall be deemed legal if it is drawn up between consenting parties who accept it as complete and unconditional and some external manifestation of assent communicates the acceptance of an offer.(Burrows, Finn, & Todd, 2202, p. 60)
 Print     
  • eConstruction
  • Construction Articles
  • Forums
  • Download Page
  • Production Rates
  • Job Page
  • PM Documentation
 To contribute to this community webpage requires registration.  

    
 Production Rates Repository  

 

< BACK  1 of 16  NEXT >

Excavate and Remove
Task / DescriptionSlow  Ave  Fast   Units
 Excavate Spoil Heaps to Transport, 0.6m3 bucket, Sand/Soil14.5 20.0 25.6  m3/hr
 Excavate Spoil Heaps to Transport, 0.6m3 bucket, Gravel Beds15.2 20.4 25.6  m3/hr
 Excavate Spoil Heaps to Transport, 0.6m3 bucket, Clay/Chalk12.3 18.5 23.2  m3/hr
 Excavate Spoil Heaps to Transport, 0.6m3 bucket, Boulder Clay11.2 16.9 21.3  m3/hr
 Excavate Spoil Heaps to Transport, 1.1m3 bucket, Sand/Soil25.4 30.3 35.7  m3/hr
 Excavate Spoil Heaps to Transport, 1.1m3 bucket, Gravel Beds25.6 31.3 37.0  m3/hr
 Excavate Spoil Heaps to Transport, 1.1m3 bucket, Clay/Chalk22.5 27.8 33.3  m3/hr
 Excavate Spoil Heaps to Transport, 1.1m3 bucket, Boulder Clay18.9 24.4 30.3  m3/hr
 Load Spoil to Barge, capacity 2,000m3-  8.0 -   hrs
 Load Spoil to Barge, capacity 1,500m3-  6.5 -   hrs
 Load Spoil to Barge, capacity 1,000m3-  5.5 -   hrs
 Spoil conveyor, 600mm belt, 150m/min-  260.0 -   m3/hr

Posted @ 6/22/2006 1:51:51 AM by gush@win.co.nz | COMMENTS (0)


Concrete Road surfacing
Task / DescriptionSlow  Ave  Fast   Units
 Concrete Road surfacing, Kerbs or Side Haunches-  0.4 -   m3/hr
 Concrete Road surfacing, 150mm thick-  12.5 -   m2/hr
 Concrete Road surfacing, 200mm thick-  7.7 -   m2/hr
 Concrete Road surfacing, 300mm thick-  6.7 -   m2/hr

Posted @ 6/23/2006 12:56:08 AM by gush@win.co.nz | COMMENTS (0)


Basecourse Production Rates

We have found these production rates a good rule of thumb for the construction of Basecourse

 

Urban environment:

 

Spread & Compact Production = 30m3/hr

Trimming Production = 250m2/hr

 

Rural environment:

 

Spread & Compact Production = 50m3/hr

Trimming Production = 350m2/hr


Posted @ 5/25/2006 3:44:58 PM by gush@win.co.nz | COMMENTS (2)


Working Platforms
Task / DescriptionSlow  Ave  Fast   Units
 Metal KwikStage, 5 Boards with 2m lifts11.1 11.9 12.5  m run/hr
 Metal KwikStage, 5 Boards with 3m lifts9.1 10.0 10.5  m run/hr
 Metal KwikStage, House Scaffold with 3 lifts2.8 3.2 3.8  m run/hr
 Metal Tube and Fittings, 5-6 Boards wide3.2 3.7 4.6  m run/hr
 Tube and Fitting Platforms, 50-250m310.6 12.5 18.5  m3/hr
 Tube and Fitting Platforms, 250-1000m318.5 22.5 24.5  m3/hr
 Tube and Fitting Platforms, over 1000m324.5 30.0 33.5  m3/hr
 Tube and Fitting Platforms, striking-  200.0 -   % x erect

Posted @ 6/23/2006 2:06:37 AM by gush@win.co.nz | COMMENTS (0)


Waterproofing
Task / DescriptionSlow  Ave  Fast   Units
 Asphalt coatings, horizontal surfaces3.5 4.2 5.8  m2/hr
 Asphalt coatings, vertical surfaces1.2 1.7 2.2  m2/hr
 Bituminous Brushed application, 2 coats4.8 5.0 6.3  m2/hr
 Bituminous Brushed application, 3 coats3.3 3.5 4.4  m2/hr
 Bituminous Sheets, horizontal surfaces3.8 4.0 4.8  m2/hr
 Bituminous Sheets, vertical surfaces3.3 3.5 4.2  m2/hr
 Polythene Sheets, horizontal surfaces-  20.0 -   m2/hr
 Bentonite Sheets, horizontal surfaces18.7 25.0 31.3  m2/hr
 Bentonite Sheets, vertical surfaces11.2 15.0 17.3  m2/hr
 Epoxy Based application, 1 coat-  75.0 -   m2/hr
 Epoxy Based application, 2 coat-  38.0 -   m2/hr

Posted @ 6/23/2006 2:05:21 AM by gush@win.co.nz | COMMENTS (0)


< BACK  1 of 16  NEXT >
 Print     
 Sponsors  

 

 Print