As with all programs there are a number of ways of doing things. A good practice would be to set up a project called pricing standards which should be copied in using the utility’s menu from a project that you have priced previously and preferably won the bid. By doing this you then have a strong starting point for a new contract that is similar in nature. For the next project; copy the recourse file into the new project from the utility menu once again, then import the new project schedule of items from excel (Copy & Paste) into the estimating and pricing form of Methvin.
For fast and confident pricing go to your pricing standards project and copy the lines of ‘pricing details’ form and then paste them into your new project.
NB please remember to correct your production rates and update your resource file values before submitting your bid.
Hope this helps
Regards